Belconnen Trunk Sewer Augmentation

Girri Birrang, in collaboration with Diona, completed the Belconnen Trunk Sewer Augmentation project to update the region's aging sewer system. This enhancement was crucial to accommodate the growing needs of the Belconnen, Gungahlin, and Hall areas.

Client: Diona

End Client: ICON Water

Location: Belconnen, ACT

Timeframe: 2020 – 2023

Project Value: Approx. $3 million

Project Need

The need for the Belconnen Trunk Sewer Augmentation arose from the necessity to modernise the 1960s infrastructure to support the expanding communities. The upgrade ensures a more resilient and efficient sewer system, catering to the current and future demands of the region.

Our Focus

Completion of a pipeline to increase sewer capacity.

Employing both traditional trenching and trenchless technology for pipeline installation.

Constructing a pipe bridge over Ginninderra Creek, incorporating stringent environmental measures.

Building multiple maintenance holes for easy access and upkeep of the pipeline.

Installing odour control units to minimise community impact and enhance environmental sustainability.

Our Objectives

Navigating environmental and technical challenges, such as creek flooding and unexpected weather conditions.

Prioritising sustainability, evidenced by repurposing removed trees for habitat enrichment at the National Zoo and Aquarium.

Discover how Girri Birrang can bring your project to life. Contact us today to learn more about our expertise and services.